City Commission approved a sewer rate increase

On November 2, 2016 the City Commission approved a sewer rate increase. The increase is due to the upgrade at the Waste Water Treatment Plant. The engineers are currently working on the design phase.

The sewer rate will increase effective December 1, 2016. The amount of the increase is based upon the meter size. Most residential homes have a 5/8 meter.

Meter Size                   Old                  New                 Difference      

5/8                               13.26               15.12               1.86                            

3/4                               13.57               15.47               1.90                

1                                  13.75               15.68               1.93    

1 ½                              14.29               16.29               2.00    

2                                  15.70               21.20               5.50    

3                                  18.06               31.61               13.55  

4                                  27.44               45.28               17.84  

6                                  41.51               80.94               39.43  

8                                  55.60               127.88             72.28  

10                                79.07               189.77             110.70

Sewer usage cost will also increase from $2.83 per 1,000 gallons to $2.94 per 1,000 gallons, an 11 cent increase.